Start of works |
|
The Matrix Modules arrive flat packed on site - Requiring minimal contruction |
|
The excavation is complete - The area is lined with Geotextile and a sand layer is installed to protect the tanking membrane |
|
A geotextile layer is laid over the sand layer in the bottom of the excavation |
|
Perspective of the excavation area |
|
The tanking membrane was constructed to spec off site and installed in the bottom of the excavation area |
|
Completing laying of the membrane - Enough membrane has been allocated to cover the sides of the Matrix Tank |
|
A layer of sand is installed in the tank to protect the membrane and Matrix tanking cells |
|
The Matrix Cells are installed in the excavation area |
|
Perspective of the cell installation |
|
Perspective of the cell installation #2 |
|
The tank is wrapped in Geotextile and inspection points installed |
|
The tank is backfilled with sand to protect the tank and aid in bio filtration of surface water into the Modules |
![]() Landscape features over the top of the Matrix Tank. 347,000L of water tank exist under the grounds of the park |
![]() The final landscaping is finished and the surroundings are completed |